Diesel generator set
A generator that runs light burns more fuel for every kWh, and wears faster too.
Tower loads are small, so most site generators (the DG set, in tower terms) spend their life at a quarter of their rating or less. Fuel per kWh climbs as load drops, and the engine never gets hot enough to burn clean. The twin puts a price on each hour run light and shows what battery-hybrid cycling would save.
20 kVA / 16 kW prime, 400 V 3-phase, 50 Hz, 1,500 rpm
Built and run to ISO 8528-1 (prime and standby ratings)
- Fuel per kWh at 25%
- 0.54 L/kWh
- Fuel per kWh at 75%
- 0.34 L/kWh
- Hybrid cycling, fuel
- 35% less
- Hybrid cycling, run hours
- 67% fewer
Anatomy and nameplate
- 1Voltage and current per phase. Real power from the phases, not the controller’s rounded kW.
- 2Engine speed. 1,500 rpm on a 4-pole alternator is 50 Hz. Drift means the governor is working hard.
- 3Coolant temperature. Checked against what the load and outside air should give.
- 4Oil pressure. Read against speed and temperature. A reading with the engine stopped is a sender fault.
- 5Start battery voltage. 12 V. The dip while cranking shows a weak battery before a failed start.
- 6Run hours and start count. Service is due on hours, not on the calendar.
- 7Fuel level. From the tank sender, set against the burn the load explains.
- 8Controller alarms and mode. Auto, manual or off. A set left in manual will not start in an outage.
| Rating | |
|---|---|
| Prime rating | 20 kVA / 16 kW at 0.8 power factor |
| Standby rating | 22 kVA / 17.6 kW |
| Output | 400 V, 3-phase, 50 Hz |
| Current at prime | 28.9 A per phase |
| Speed | 1,500 rpm, 4-pole alternator |
| Engine and fuel | |
| Engine | 4-cylinder diesel, water cooled |
| Starting | 12 V electric start |
| Fuel at full prime load | 5.0 L/h (0.314 L/kWh) |
| Fuel at 75% load | 4.06 L/h (0.339 L/kWh) |
| Fuel at 25% load | 2.14 L/h (0.536 L/kWh) |
| Fuel at no load | 1.18 L/h |
| Service interval | 500 run hours |
| Reference site | |
| Run hours a year | 1,081 h over 320 outages |
| Average load | 3.3 kW (20% of prime) |
| Fuel a year | 2,125 L |
Telecom site power chain
The grid or the generator feeds the site through the transfer switch. The rectifier makes −48 V DC for the radios and keeps the battery charged. The air conditioner keeps the battery cool.
- Air
- AC power
- −48 V DC
- Diesel
- Has its own twin page
The physics
The equations behind every curve on this page.
Power
P = √3 · V · I · PF
Real power from the three phases, not the controller’s rounded kW.
Load factor
LF = P / P_prime
Measured against the 16 kW prime rating, not the standby rating.
Fuel (Willans line)
F = a · P_prime + b · P
Burn has a fixed part that does not drop with load: 1.18 L/h at no load.
Fuel per kWh
F / P = a / LF + b
At 25% load it is 1.7 times the full-load figure.
Frequency
f = poles · rpm / 120
4 poles at 1,500 rpm gives 50 Hz.
Hybrid cycling
r = P_L / (P_L + P_charge · η_rt)
Share of the day the engine runs when it charges the battery and then stops.
Fuel per kWh
Every engine burns some fuel just to turn over. At low load that fixed part is spread over few kWh. Tower sites run their generators light almost all the time.
Litres per kWh against load
20 kVA / 16 kW prime generator
- Fuel per kWh, Willans line
- Full load
- 5.0 L/h
- No load
- 1.18 L/h
- 25% against full load
- 1.71×
An engine burns a fixed amount just to turn over. At a quarter load that fixed part is spread over few kWh, so every kWh costs far more fuel.
F = a·P_prime + b·P F/P = a/LF + b
Run hours by load band, one year
1,081 run hours at the reference site
- Hours in each 10% band
- Hours under 30% load
- 1,081 h (100%)
- Average load
- 20% of prime
Tower loads are small. Every hour this generator ran was under 30% of its rating, where fuel per kWh is high and the engine runs cool.
LF = P / P_prime, P = √3·V·I·PF
Battery-hybrid cycling
Instead of running light all day, run the engine near its best load to carry the site and charge the battery, then stop it and let the battery carry the site.
One day: running continuously against battery-hybrid cycling
4 kW site, lithium string cycled 20–90%
- Output, continuous
- Output, cycled
- Fuel, continuous (right axis)
- Fuel, cycled (right axis)
- Run hours a day
- 24 h → 7.9 h
- Litres a day
- 51 L → 33 L
- Starts a day
- 4.3
Run the engine hard to charge the battery, then stop it. The same day takes 35% less fuel and 67% fewer run hours.
r = P_L / (P_L + P_charge · η_rt) fuel = r · F(0.8·P_prime) against F(P_site)
What cycling saves, by site load
Generator at 80% load while it runs
- Run hours saved
- Fuel saved, lithium
- Fuel saved, VRLA
The lighter the site, the more cycling saves. A battery that loses less energy on the round trip keeps more of the saving.
η_rt = 93% lithium, 82% VRLA
Failure modes
What breaks, what it looks like, what the twin does about it.
| Failure mode | The physics | Signals that show it | How the twin catches it |
|---|---|---|---|
| Wet stacking | Below about 30% load the cylinders run cool. Unburned fuel and soot build up in the exhaust. | Hours below 30% load. Low coolant temperature while loaded. Oily residue at the exhaust. | Counts hours by load band and flags the sites that need a load-bank run or hybrid cycling. |
| Failed start | A weak start battery, fuel starvation or a latched fault stops the engine from starting. | Start battery dip while cranking. Start attempts with no run. Long crank times. | Tracks every start, and flags failed or slow starts and a falling start battery. |
| Overheating | A fouled radiator, a failed fan belt or low coolant leaves heat in the engine. | Coolant temperature above the model for the load and outside air. | Compares coolant temperature with the expected value at that load and ambient. |
| Low oil pressure | Wear, low oil or a faulty sender. | Oil pressure against speed and temperature. | Flags readings that are impossible with the engine stopped (a sender fault) apart from real low pressure. |
| Service overdue | Oil and filters age with run hours. | Run hours since the last service. | Drafts the service work order at 500 run hours, not on the calendar. |
What the twin does not do
- The twin does not start or stop the engine.
- Remote start only through your own controller and policy, with a person approving.
How we catch it early
A physics twin and a PINN, working on one diesel generator set.
The twin is a set of equations for this machine, tuned to its nameplate. Give it the flow, speed and conditions and it returns what every reading should be. It always gives the same answer for the same inputs.
A physics-informed neural network, or PINN, sits on top. It is trained on the plant’s own data and it is penalized whenever it breaks a physics rule. So it can only learn what the equations leave out: wear, fouling, friction. It cannot invent an answer that the machine could never produce.
Step 1
Measure
Flow, pressure, current, temperature, vibration. Whatever the asset already has.
Step 2
Physics twin
The equations of this machine, set to its nameplate. It says what the readings should be right now.
Step 3
Residual
Measured minus expected. Demand, weather and speed are already taken out.
Step 4
PINN
A small neural network that learns the cause of the gap, under the physics rules.
Step 5
Finding
A named cause, a date, and the kWh or hours at stake. An engineer reviews it.
loss = (measured − predicted)² + λ · (physics residual)²
The second term is the rulebook. It is zero when the network obeys the equations.
Why this beats black-box AI
A black-box model learns patterns from history. It needs examples of each failure, and it goes quiet when the pump runs at a point it has not seen. The twin starts from physics, so it works on day one. The PINN adds what physics cannot know about this particular machine.
That is also what makes the savings countable. The baseline is a calculation, not a guess, so the gap between baseline and meter is a number a customer can check.
What the twin checks on this asset
- Litres per kWh against the Willans line: 0.60 L/kWh at this site’s 20% load
- Hours below 30% load: 1,081 of 1,081 run hours
- Coolant temperature against load and outside air
- Start success and start-battery dip on every start
- Oil pressure plausibility, running and stopped
| Fixed alarm | Black-box AI | Twin + PINN | |
|---|---|---|---|
| Needs failure history to learn | No | Yes, lots | No |
| Says what is wrong | No | Rarely | Yes, by name |
| Works at a flow it has never seen | No | Often fails | Yes, the equations still hold |
| Puts a number on the saving | No | No | Yes, in kWh and dollars |
| Lead time on slow wear | Late | Varies | Weeks to months |
| Every number can be traced | Yes | No | Yes, to an equation |
What the twin puts a number on
Energy and cost, from the equations.
Fuel per kWh, 25% against 75% load
0.54 against 0.34 L/kWh
1.58 times the fuel for each kWh at a quarter load
Hybrid cycling, 4 kW site
35% less fuel
51 L a day down to 33 L. 6,557 L a year where the generator carries the site all year.
Run hours saved
67% fewer
24 run hours a day down to 7.9, with 4.3 starts a day
Cost of running light
$1,119 a year
932 L more than the same kWh at 75% load, at $1.20 per litre
What we do for you
We watch it. We catch it. We prove it.
Our reliability engineers run the twin on your diesel generator set, review every finding, and help your crew fix it. After the repair we compare the meter to the baseline and write the result in the ledger.
More assets
More from telecom towers, then the lead asset of each other industry.
- Telecom towersRectifier systemOpen
- Telecom towersBattery bankOpen
- Telecom towersShelter coolingOpen
- Telecom towersFuel tankOpen
- Telecom towersTransfer switch and mainsOpen
- Water & wastewaterCentrifugal pumpOpen
- ManufacturingRotary screw air compressorOpen
- Buildings & data centersWater-cooled centrifugal chillerOpen
- Energy & utilitiesPower transformerOpen
- PharmaceuticalWFI distribution loopOpen
- Oil & gasReciprocating gas compressorOpen